Medical School & Simulation Center
A new medical school building with simulation suites, finished and furnished before an admitted class arrived for orientation.
- Owner
- Confidential
- Region
- U.S. Southeast
- Market
- Education
- Capital value
- $165M
- Size
- 210,000 SF
- Delivery
- CM at-risk
- Duration
- 30 months
- Completed
- 2024
What was at stake.
The school had admitted its class and scheduled an accreditation site visit before the building was topped out. Simulation equipment, AV systems and furniture came from separate vendors on separate contracts. None of those dates lived in the construction schedule.
How we controlled it.
What our schedulers and cost engineers did on this project.
Owner work in P6
We loaded owner-furnished equipment, AV, IT and furniture into the integrated schedule beside the contractor's work.
Room readiness
Each simulation suite had its own readiness milestone, tied to the walkthrough plan for the accreditation visit.
Early warnings
Biweekly updates flagged two vendor slips months ahead, with resequencing options priced before they became delays.
Move-in plan
Faculty move, IT cutover and training were scheduled as real work ending on orientation day.
The result.
Students do not care which contract was late. One schedule meant one owner of every date.
Lead scheduler, AdenTurton



More from Buildings.
All Buildings
Education · In progressK-12 School Construction Bond ProgramU.S. Mid-Atlantic & Northeast · $690M · 54 months
Healthcare · In progressTrauma Center & Critical Care TowerU.S. Mid-Atlantic & Northeast · $980M · 52 months
Commercial & Mixed-Use · In progressUrban Mixed-Use BlockU.S. Southeast · $760M · 38 months
Planning something like this?
Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.