Education · U.S. Southeast

Medical School & Simulation Center

A new medical school building with simulation suites, finished and furnished before an admitted class arrived for orientation.

Owner
Confidential
Region
U.S. Southeast
Market
Education
Capital value
$165M
Size
210,000 SF
Delivery
CM at-risk
Duration
30 months
Completed
2024
The challenge

What was at stake.

The school had admitted its class and scheduled an accreditation site visit before the building was topped out. Simulation equipment, AV systems and furniture came from separate vendors on separate contracts. None of those dates lived in the construction schedule.

Schedule30 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Owner work in P6

We loaded owner-furnished equipment, AV, IT and furniture into the integrated schedule beside the contractor's work.

02

Room readiness

Each simulation suite had its own readiness milestone, tied to the walkthrough plan for the accreditation visit.

03

Early warnings

Biweekly updates flagged two vendor slips months ahead, with resequencing options priced before they became delays.

04

Move-in plan

Faculty move, IT cutover and training were scheduled as real work ending on orientation day.

Results

The result.

On dateReady before orientation
$165MCapital controlled
30Months on one baseline
1Schedule for every contract

Students do not care which contract was late. One schedule meant one owner of every date.

Lead scheduler, AdenTurton
Education