Washington, D.C. · Est. 2021 Project controls & construction IT CareersPartnersProgram RatesMedia512-908-5223Data date
Water & Wastewater · U.S. Mid-Atlantic & Northeast

Combined Sewer Overflow Storage Tunnel

A deep storage tunnel and two shafts that will capture combined sewer overflows before they reach the river.

Owner
Confidential
Region
U.S. Mid-Atlantic & Northeast
Market
Water & Wastewater
Capital value
$890M
Size
3.1-mile tunnel · 2 shafts
Delivery
Design-Build
Duration
60 months
Status
In progress · 2028
The challenge

What is at stake.

Tunnel boring progress varies with ground conditions, and the baseline assumed the best ground the whole way. Shaft excavation, machine assembly and the river cleanup milestones in the permit all depend on that rate. The owner needed honest production forecasting and an early view of any claim exposure.

Schedule60 monthsIn progress · finish 2028
202320242025202620272028
Today
Start
2023
Planned finish
2028
Time elapsed
58%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Production tracking

Daily ring counts and advance rates are compared to the baseline by geologic reach, so slow ground shows up as days, not excuses.

02

Risk by reach

Monte Carlo analysis models advance rates by ground type, giving P50 and P80 dates for hole-through and substantial completion.

03

Earned value

A cost-loaded schedule tracks SPI and CPI monthly, separating ground-related variance from performance variance.

04

Claims readiness

Contemporaneous records and windows analysis are kept current, so any differing site condition claim can be answered on facts.

Results

Where it stands.

$890MCapital under control
60Months on one baseline
3.1 miTunnel tracked ring by ring
P80Hole-through date reported

A tunnel does not slip all at once. It slips a few feet a day, and you only see it if you count every ring.

Senior scheduler, AdenTurton
Water & Wastewater

Planning something like this?

Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.