Water Reclamation Facility & Outfall

A 40 MGD water reclamation facility and outfall, brought to permitted flow before a consent decree deadline.

Owner
Confidential
Region
U.S. West
Market
Water & Wastewater
Capital value
$560M
Size
40 MGD
Delivery
Progressive Design-Build
Duration
44 months
Completed
2026
The challenge

What was at stake.

The utility was under a consent decree with daily penalties after the deadline. Progressive design-build meant the guaranteed price and the schedule were set in stages, and early packages were already behind. The utility needed a defensible forecast for the regulator and a plan to recover the lost months.

Schedule44 monthsCompleted 2026
2023202420252026
Start
2023
Finish
2026
Duration
44 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Staged baselines

Each design-build phase got its own baselined P6 schedule, rolled into one program view against the decree date.

02

Recovery plan

We resequenced process trains so the first train reached permitted flow while the later trains were still in construction.

03

Startup in the plan

Process startup, seeding and performance testing were scheduled as real durations, not a single milestone at the end.

04

Regulator reporting

Quarterly reports to the regulator used the same data as the internal update, so there was only one version of the truth.

Results

The result.

AheadOf the consent decree date
$560MCapital controlled
44Months, design to flow
40 MGDPermitted capacity

A consent decree turns a schedule into a legal document. Every date we reported had to be one we could prove.

Recovery lead, AdenTurton