Washington, D.C. · Est. 2021 Project controls & construction IT CareersPartnersProgram RatesMedia512-908-5223Data date
Power & Renewables · U.S. Midwest & Mountain

Transmission Line & Substation Upgrade Program

A 180-mile transmission line and six substation upgrades, delivered as one program for new load waiting on the wires.

Owner
Confidential
Region
U.S. Midwest & Mountain
Market
Power & Renewables
Capital value
$1.05B
Size
180 miles · 6 substations
Delivery
EPC
Duration
48 months
Status
In progress · 2027
The challenge

What is at stake.

Outage windows on the existing grid are scarce and booked months ahead. Landowner access, environmental windows and long-lead breakers and transformers all sit on the critical path. New industrial and data center load is waiting to connect.

Schedule48 monthsIn progress · finish 2027
20232024202520262027
Today
Start
2023
Planned finish
2027
Time elapsed
72%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Program IMS

Line segments, substations, outages and energization sit in one integrated P6 schedule tied to each customer's connection date.

02

Outage planning

Outage requests are scheduled with their prerequisites, so no window is booked before the work is ready for it.

03

Long-lead equipment

Breakers, transformers and relay panels are tracked from factory to site, with float to the substation they serve.

04

Risk and EVM

Monthly Monte Carlo analysis and earned value give leadership P80 energization dates and an honest cost forecast.

Results

Where it stands.

$1.05BCapital under control
180 miLine on one IMS
48Months of program
P80Energization dates reported

An outage window is the scarcest thing on a grid program. We never let one go to waste.

Program controls manager, AdenTurton
Power & Renewables

Planning something like this?

Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.