Behavioral Health Hospital Replacement

A 160-bed behavioral health hospital that replaced an aging facility, with every patient transferred in a single planned weekend.

Owner
Confidential
Region
U.S. Mid-Atlantic & Northeast
Market
Healthcare
Capital value
$310M
Size
240,000 SF · 160 beds
Delivery
CM at-risk
Duration
30 months
Completed
2025
The challenge

What was at stake.

Behavioral health patients cannot be moved in waves without clinical risk, so the transfer had to happen once. That meant the building, the state licensing survey, ligature-resistant fit-out, security systems and staff training all had to finish before one fixed weekend. The contractor schedule ended at substantial completion and said nothing about the weekend that mattered.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Schedule to the move

We extended the P6 baseline past substantial completion to licensing, staff orientation and the transfer weekend, so the real finish line was on the critical path.

02

Safety fit-out tracked

Ligature-resistant hardware, anti-ligature doors and security glazing were tracked as long-lead items tied by logic to each unit.

03

Monthly float review

Every update reported total float to the transfer weekend, so a slip in any unit showed up as lost days, not as a vague concern.

04

Move scripted

The transfer itself was scheduled hour by hour with clinical and security leads, then walked through twice before the weekend.

Results

The result.

1 weekendEvery patient transferred
$310MCapital controlled
30Months on one baseline
160Beds opened at once

Substantial completion is the contractor's finish. The owner's finish was a weekend, so that is where the schedule ended.

Lead scheduler, AdenTurton
Healthcare