Healthcare · U.S. Texas

Freestanding Emergency Department Program

Six freestanding emergency departments delivered as one program, each opening in the month the owner had committed to.

Owner
Confidential
Region
U.S. Texas
Market
Healthcare
Capital value
$140M
Size
6 sites
Delivery
Program delivery
Duration
22 months
Completed
2024
The challenge

What was at stake.

Six sites, three general contractors and six separate licensing inspections. Each contractor reported progress its own way, so leadership saw six different stories and no program view. Opening dates had been announced to communities before two of the sites had permits.

Schedule22 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
22 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

One program WBS

We set a common WBS and activity coding across all six schedules, so every site reported the same milestones in the same terms.

02

Permits as logic

Permit, utility and licensing milestones were loaded as logic, not as dates typed in a spreadsheet, so their real effect on opening showed.

03

Program dashboard

A single Power BI view showed each site's forecast opening, float and open risks, refreshed from the XER files every two weeks.

04

Repeat-site library

Lessons from the first two sites went into a logic library the later sites used from day one.

Results

The result.

6 of 6Sites opened in the committed month
$140MCapital controlled
22Months, first site to last
1Program schedule, six sites

Six schedules that disagree are worse than none. Once every site spoke the same coding, the program could finally be read.

Program controls manager, AdenTurton
Healthcare