Standards & quality · 14 checks

No date goes untested.

A date is only as good as the network under it. Ours, the contractor’s or yours, every schedule we touch runs the same fourteen checks, then goes to a second senior reviewer.

The checks

Fourteen checks, one line each.

Modeled on the DCMA 14-point schedule assessment. Software runs them in minutes. A senior scheduler reads every result and explains it.

LogicCheck 01

Every unfinished activity needs a predecessor and a successor. Open ends hide work nobody has planned yet.

LeadsCheck 02

Negative lags let work start before its predecessor finishes. They compress time on paper and nowhere else.

LagsCheck 03

Long waits typed into a tie hide real work, such as cure time or submittal review, that deserves its own activity.

Relationship typesCheck 04

Finish-to-start ties should carry most of the network. Heavy use of other types makes the path hard to trace.

Hard constraintsCheck 05

Must-finish-on dates override logic. Use too many and the schedule reports the date someone wanted.

High floatCheck 06

Months of float usually means a missing successor, not a lucky cushion. We find the broken tie.

Negative floatCheck 07

Negative float means the plan already misses a required date. It needs a recovery path, not silence.

High durationCheck 08

Very long activities cannot be measured honestly. We break them into pieces the field can progress.

Invalid datesCheck 09

No forecast dates in the past and no actual dates in the future, measured against the data date.

ResourcesCheck 10

Where the contract calls for loading, activities carry the labor, quantities or cost that earned value needs.

Missed tasksCheck 11

Work that should have finished by the data date and did not. A rising count is the earliest warning of a slip.

Critical path testCheck 12

We add delay to a critical activity. If the finish date does not move by the same amount, the path is broken.

CPLICheck 13

The critical path length index shows whether the remaining path can still make the required finish.

BEICheck 14

The baseline execution index compares work finished with work planned to finish. It shows whether the plan is being worked.

Frameworks

The methods we follow.

Recognized methods and guidance we work to. They are not certifications or memberships, and we never present them as one.

Critical path method

The foundation under every schedule we build or review: activities, logic, durations, float and a path you can trace.

Method

AACE recommended practices

We follow AACE International recommended practices for planning, schedule risk and forensic schedule analysis.

Practice guidance

GAO Schedule Assessment Guide

Its best practices for a reliable schedule shape how we score a baseline and write review findings.

Assessment guide

Earned value, EIA-748

We follow the EIA-748 guidelines so SPI, CPI and the estimate at completion tell one consistent story.

Guidelines
Peer review

Two signatures on every deliverable.

Every baseline, update narrative, risk run and claim exhibit is reviewed by a senior specialist who did not build it, before it reaches you.

  • Logic and datesThe reviewer reruns the checks and traces the critical path from the data date to the finish.
  • Numbers that tie outCosts, quantities and earned value reconcile to the source files and the latest pay application.
  • Plain-English narrativeFindings say what moved, why it moved and what leadership needs to decide.
Confidentiality

Your files stay yours.

Schedules, cost reports and claim files are commercially sensitive. We treat them that way from the first email.

01

Need-to-know access

Only the people assigned to your engagement can open your files, and access ends when the work does.

02

Controlled sharing

Files move through the transfer method you approve, never through personal email or public links.

03

Confidential by default

We never name clients or publish project details. Every project on this site is shown with the owner as Confidential.

Talk to a scheduler

Put your schedule to the test.

Send us an XER or MPP file. We run the checks and tell you what we find. A senior project controls lead replies within one business day.