Oil, Gas & Chemicals · U.S. Texas

Low-Carbon Ammonia Plant

A low-carbon ammonia plant built from modules fabricated overseas, controlled to an offtake contract start date.

Owner
Confidential
Region
U.S. Texas
Market
Oil, Gas & Chemicals
Capital value
$1.6B
Size
1 MTPA ammonia
Delivery
EPC
Duration
44 months
Status
In progress · 2028
The challenge

What is at stake.

Process modules are fabricated in overseas yards and shipped in a limited marine delivery window. Late modules mean a missed window and months of delay. The offtake contract has a fixed start, and the owner needs a forecast that reflects real fabrication progress, not yard optimism.

Schedule44 monthsIn progress · finish 2028
2025202620272028
Today
Start
2025
Planned finish
2028
Time elapsed
43%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Yard progress checks

Module fabrication progress is measured against earned value rules at the yards, not taken from the fabricator's percent complete.

02

Marine window logic

Load-out, sailing and set dates are tied to each module, so a late module shows its effect on the whole site.

03

Commissioning plan

Systems are tracked from mechanical completion through precommissioning, commissioning and performance testing.

04

Risk analysis

Monthly Monte Carlo analysis gives P50 and P80 first production dates for the board and the offtaker.

Results

Where it stands.

$1.6BCapital under control
44Months to production
1 MTPACapacity in the plan
P80First production reported

A fabricator's percent complete is a hope. Earned value measured in the yard is a fact.

Cost controls lead, AdenTurton
Oil, Gas & Chemicals