Onshore Wind Farm & Collector Substation

A 400 MW wind farm and collector substation, at commercial operation before a tax credit deadline.

Owner
Confidential
Region
U.S. Texas
Market
Power & Renewables
Capital value
$560M
Size
400 MW · 110 turbines
Delivery
EPC
Duration
22 months
Completed
2023
The challenge

What was at stake.

The tax credit deadline was fixed, and missing it would change the project's economics. Turbine deliveries came in convoys, crane moves between pads took days, and high winds stopped lifting. The developer needed a schedule that modeled all of it honestly.

Schedule22 monthsCompleted 2023
20222023
Start
2022
Finish
2023
Duration
22 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Pad by pad

Each turbine pad had its own foundation, delivery, erection and commissioning activities in P6.

02

Crane path

Main crane moves were scheduled as a route across the site, so one late pad showed its effect on the rest.

03

Wind risk

Monte Carlo analysis on wind standby days showed how much margin the deadline really had.

04

Substation first

The collector substation and interconnection were scheduled so turbines could be energized as they were completed.

Results

The result.

BeforeThe tax credit deadline
$560MCapital controlled
22Months to operation
110Turbines energized

Wind is both the product and the risk. We scheduled the crane around the wind, not the other way round.

Senior scheduler, AdenTurton
Power & Renewables