Soccer Stadium & Training Complex
A 25,000-seat soccer stadium and training complex, scheduled to host a home opener the league has already published.
- Owner
- Confidential
- Region
- U.S. West
- Market
- Sports & Entertainment
- Capital value
- $450M
- Size
- 25,000 seats · 6 fields
- Delivery
- Design-Build
- Duration
- 34 months
- Status
- In progress · 2027
What is at stake.
The league fixes the home opener a year ahead, and there is no alternate venue. Grass must be grown and established, broadcast systems certified and the stadium inspected for occupancy before the first match. Design-build packages are still being released while steel goes up.
How we control it.
What our schedulers and cost engineers are doing on this project.
Opener as milestone
The home opener is the controlling milestone, with turf grow-in, broadcast certification and life safety inspections scheduled back from it.
Package release logic
Each design package is tied by logic to the work it releases, so late design shows up as lost float immediately.
Monte Carlo
Monthly risk analysis gives P50 and P80 substantial completion dates against the opener.
Earned value
A cost-loaded schedule tracks SPI and CPI so leadership sees cost trends while there is still time.
Where it stands.
Grass needs months to establish. If the turf is not on the critical path, the opener is already late.
Senior scheduler, AdenTurton