Aerospace Components Assembly Plant

A 620,000 SF aerospace assembly plant, ready for its first shipset on the date promised to the airframer.

Owner
Confidential
Region
U.S. Southeast
Market
Manufacturing
Capital value
$290M
Size
620,000 SF
Delivery
Design-Build
Duration
26 months
Completed
2025
The challenge

What was at stake.

Assembly tooling needs super-flat floors, overhead cranes and stable temperature before it can be set. The tooling vendor had a fixed installation slot, and the first shipset delivery carried contract penalties. Floor flatness testing and crane certification were not in the schedule at all.

Schedule26 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
26 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Tooling backward

We scheduled backward from the tooling slot through crane certification, floor testing and HVAC balancing.

02

Floor as critical work

Slab pours were sequenced by tooling zone, with flatness testing and remediation as named activities.

03

Biweekly updates

Updates every two weeks against the baseline, with a narrative on float to the tooling slot.

04

Change control

Tooling layout changes were priced and their schedule effect shown before approval.

Results

The result.

On dateTooling slot met
$290MCapital controlled
26Months to first shipset
620K SFAssembly plant

The tooling vendor had one slot and no second chances. The schedule started there and worked back.

Senior scheduler, AdenTurton
Manufacturing