Food & Beverage · U.S. Texas

Aseptic Beverage Processing Plant

An aseptic beverage plant with six filling lines, controlled from first steel to sterility validation.

Owner
Confidential
Region
U.S. Texas
Market
Food & Beverage
Capital value
$380M
Size
6 aseptic lines
Delivery
EPCM
Duration
30 months
Status
In progress · 2027
The challenge

What is at stake.

Aseptic lines are finished only when sterility validation passes, and validation runs take weeks per line. The EPCM schedule shows equipment set but treats commissioning and validation as one milestone. Product launch dates with retailers are already set.

Schedule30 monthsIn progress · finish 2027
202520262027
Today
Start
2025
Planned finish
2027
Time elapsed
56%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Validation in the baseline

IQ, OQ and PQ for each line are scheduled as real activities with durations, so the launch date reflects the work it depends on.

02

Commissioning levels

Utilities, process and filling equipment are tracked from L1 factory testing to L5 integrated runs.

03

Risk on launch

Monthly Monte Carlo analysis gives P50 and P80 launch dates per line, with the risks that move them.

04

Earned value

Engineering, procurement and construction are measured on one cost-loaded schedule, so CPI and SPI trends are visible by line.

Results

Where it stands.

$380MCapital under control
30Months to launch
6Aseptic lines tracked to PQ
P80Launch date by line

Mechanical completion feels like a finish. In aseptic work it is barely the halfway point.

Lead scheduler, AdenTurton