Cell & Gene Therapy Manufacturing Facility

A cell and gene therapy manufacturing facility, qualified in time to supply patients in clinical trials.

Owner
Confidential
Region
U.S. Mid-Atlantic & Northeast
Market
Life Sciences
Capital value
$450M
Size
210,000 SF
Delivery
EPCM
Duration
30 months
Completed
2025
The challenge

What was at stake.

Clinical trial timelines depended on the facility producing its first engineering batch on time. Cleanrooms, single-use equipment and quality systems all had to be qualified before any product could be made. The EPCM schedule showed construction finishing but left qualification as one line.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Qualification in the baseline

Commissioning, IQ, OQ and PQ for each suite were scheduled as real work tied to the first engineering batch.

02

Cleanroom certification

Each suite was tracked through certification and environmental monitoring, with float to its first batch.

03

Earned value

A cost-loaded schedule gave leadership SPI and CPI by suite every month.

04

Risk to supply

Monte Carlo analysis on the first batch showed P50 and P80 dates the clinical team could plan around.

Results

The result.

On dateFirst engineering batch
$450MCapital controlled
30Months to first batch
210K SFGMP facility

In cell therapy the building is half the job. Qualification decides the finish, so qualification is in the baseline.

Lead scheduler, AdenTurton
Life Sciences