Hospitality · International

Island Resort & Villas

An island resort and villas where every material arrives by sea, scheduled from the shipping calendar outward.

Owner
Confidential
Region
International
Market
Hospitality
Capital value
$640M
Size
320 keys · 40 villas
Delivery
EPCM
Duration
40 months
Status
In progress · 2028
The challenge

What is at stake.

Every bag of cement, every window and every workers' camp supply arrives by barge. One missed sailing can delay a trade for weeks. The EPCM team needs a schedule that treats logistics as the critical path it is.

Schedule40 monthsIn progress · finish 2028
2025202620272028
Today
Start
2025
Planned finish
2028
Time elapsed
37%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Logistics schedule

Barge sailings, port handling and on-island storage are loaded into P6 and tied to the work each shipment supports.

02

Procurement tracking

Every major package is tracked from order to fabrication to sailing, with float to installation.

03

Earned value

A cost-loaded schedule reports SPI and CPI monthly, separating logistics delays from field performance.

04

Risk analysis

Monte Carlo analysis models weather and sailing risk to give P50 and P80 opening dates.

Results

Where it stands.

$640MCapital under control
40Months to opening
360Keys and villas
P80Opening date reported

On an island, the boat is the critical path. Everything else waits for the boat.

Lead scheduler, AdenTurton
Hospitality