Island Resort & Villas
An island resort and villas where every material arrives by sea, scheduled from the shipping calendar outward.
- Owner
- Confidential
- Region
- International
- Market
- Hospitality
- Capital value
- $640M
- Size
- 320 keys · 40 villas
- Delivery
- EPCM
- Duration
- 40 months
- Status
- In progress · 2028
What is at stake.
Every bag of cement, every window and every workers' camp supply arrives by barge. One missed sailing can delay a trade for weeks. The EPCM team needs a schedule that treats logistics as the critical path it is.
How we control it.
What our schedulers and cost engineers are doing on this project.
Logistics schedule
Barge sailings, port handling and on-island storage are loaded into P6 and tied to the work each shipment supports.
Procurement tracking
Every major package is tracked from order to fabrication to sailing, with float to installation.
Earned value
A cost-loaded schedule reports SPI and CPI monthly, separating logistics delays from field performance.
Risk analysis
Monte Carlo analysis models weather and sailing risk to give P50 and P80 opening dates.
Where it stands.
On an island, the boat is the critical path. Everything else waits for the boat.
Lead scheduler, AdenTurton