Hospitality · U.S. Midwest & Mountain

Mountain Lodge & Residences

A mountain lodge and residences built around short weather windows, opened for its first full season.

Owner
Confidential
Region
U.S. Midwest & Mountain
Market
Hospitality
Capital value
$290M
Size
180 keys · 60 residences
Delivery
CM at-risk
Duration
30 months
Completed
2025
The challenge

What was at stake.

Snow and access limits closed parts of the site for months each year. Structure and envelope had to be weathertight before winter, or a full season was lost. The owner had pre-sold residences against an opening season.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Weather calendar

We built a site-specific work calendar in P6, so weather-sensitive activities could only be scheduled in real windows.

02

Dry-in first

Envelope and roofing were sequenced to reach dry-in before the first snow, with interior work planned for winter.

03

Recovery ready

When an early storm cost two weeks, a priced recovery schedule protected the dry-in date.

04

Buyer reporting

Monthly reports gave the sales team dates it could share with residence buyers.

Results

The result.

First seasonOpened as planned
$290MCapital controlled
30Months through two winters
240Keys and residences

In the mountains, the calendar is the first constraint. Snow does not read the baseline.

Senior scheduler, AdenTurton