Logistics Park & Distribution Portfolio

Five large distribution buildings delivered to tenants on their lease dates, from one portfolio schedule.

Owner
Confidential
Region
U.S. Texas
Market
Commercial & Mixed-Use
Capital value
$410M
Size
5 buildings · 3,200,000 SF
Delivery
Design-Build
Duration
30 months
Completed
2024
The challenge

What was at stake.

Each building had a signed tenant with a lease start date and free rent for every late day. Tilt-wall panels, roof steel and dock equipment were shared across buildings, and one contractor's crews moved between them. The developer needed to see which building was at risk before it was too late.

Schedule30 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Portfolio schedule

All five buildings sat in one P6 schedule, with shared crews and materials coded so conflicts were visible.

02

Repeat logic

After the first building, a logic library cut schedule setup on the next four.

03

Lease dashboard

A Power BI dashboard showed each building's forecast against its lease date, refreshed every two weeks.

04

Change control

Tenant improvement changes were priced and scheduled before approval, protecting both rent dates and budgets.

Results

The result.

5 of 5Buildings on lease date
$410MCapital controlled
30Months of portfolio
3.2M SFDelivered to tenants

Free rent is a delay you can count in dollars. The dashboard showed that number before it happened.

Cost controls lead, AdenTurton
Commercial & Mixed-Use