Logistics Park & Distribution Portfolio
Five large distribution buildings delivered to tenants on their lease dates, from one portfolio schedule.
- Owner
- Confidential
- Region
- U.S. Texas
- Market
- Commercial & Mixed-Use
- Capital value
- $410M
- Size
- 5 buildings · 3,200,000 SF
- Delivery
- Design-Build
- Duration
- 30 months
- Completed
- 2024
What was at stake.
Each building had a signed tenant with a lease start date and free rent for every late day. Tilt-wall panels, roof steel and dock equipment were shared across buildings, and one contractor's crews moved between them. The developer needed to see which building was at risk before it was too late.
How we controlled it.
What our schedulers and cost engineers did on this project.
Portfolio schedule
All five buildings sat in one P6 schedule, with shared crews and materials coded so conflicts were visible.
Repeat logic
After the first building, a logic library cut schedule setup on the next four.
Lease dashboard
A Power BI dashboard showed each building's forecast against its lease date, refreshed every two weeks.
Change control
Tenant improvement changes were priced and scheduled before approval, protecting both rent dates and budgets.
The result.
Free rent is a delay you can count in dollars. The dashboard showed that number before it happened.
Cost controls lead, AdenTurton



More from Buildings.
All Buildings
Commercial & Mixed-Use · In progressUrban Mixed-Use BlockU.S. Southeast · $760M · 38 months
Commercial & Mixed-Use · 2025Office-to-Residential Tower ConversionU.S. Mid-Atlantic & Northeast · $280M · 28 months
Healthcare · In progressTrauma Center & Critical Care TowerU.S. Mid-Atlantic & Northeast · $980M · 52 months
Planning something like this?
Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.