Washington, D.C. · Est. 2021 Project controls & construction IT CareersPartnersProgram RatesMedia512-908-5223Data date
Commercial & Mixed-Use · U.S. Mid-Atlantic & Northeast

Office-to-Residential Tower Conversion

A 34-story office tower converted into 420 apartments, with first residents in on the date the lender had modeled.

Owner
Confidential
Region
U.S. Mid-Atlantic & Northeast
Market
Commercial & Mixed-Use
Capital value
$280M
Size
34 stories · 420 units
Delivery
CM at-risk
Duration
28 months
Completed
2025
The challenge

What was at stake.

Conversion work hides surprises in every floor: old slabs, new plumbing risers, new windows and a façade that has to stay safe throughout. The construction loan carried interest every month, and the lender's model depended on a lease-up date. The developer needed a schedule that held up under that pressure.

Schedule28 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
28 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Floor rhythm

We built a repeating floor cycle in P6, with demolition, risers, framing and finishes moving up the tower in sequence.

02

Surprises priced

Each concealed condition was logged, priced and its schedule effect shown within days, not at month end.

03

Lender reporting

Monthly reports gave the lender earned value, forecast completion and contingency in a format it could audit.

04

Phased occupancy

Lower floors were scheduled for temporary occupancy while upper floors were still in work.

Results

The result.

On dateFirst residents moved in
$280MCapital controlled
28Months, office to homes
420Apartments delivered

In a conversion, every floor has a secret. The schedule has to be fast enough to absorb them.

Senior scheduler, AdenTurton
Commercial & Mixed-Use

Planning something like this?

Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.