Semiconductor · U.S. Texas

Semiconductor Test & Assembly Facility

A semiconductor test and assembly facility, qualified for production on its planned date.

Owner
Confidential
Region
U.S. Texas
Market
Semiconductor
Capital value
$380M
Size
240,000 SF
Delivery
Design-Build
Duration
26 months
Completed
2024
The challenge

What was at stake.

Customer qualification of the first lines was tied to supply agreements. The building needed controlled environments, heavy power and process cooling, and equipment arrived from several countries. The contractor schedule ended at the certificate of occupancy.

Schedule26 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
26 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Past occupancy

We extended the schedule through equipment install, line qualification and customer audits, where the real finish was.

02

Imported equipment

Equipment shipments were tracked by vessel and customs status, with float to the line they served.

03

Earned value

A cost-loaded schedule tracked SPI and CPI monthly, giving leadership early warning on cost.

04

Change control

Layout changes from the process team were priced and scheduled before approval.

Results

The result.

On dateFirst lines qualified
$380MCapital controlled
26Months to qualification
240K SFFacility delivered

An occupancy certificate does not ship a single chip. The schedule had to run all the way to qualification.

Senior scheduler, AdenTurton
Semiconductor