Aviation · U.S. Southeast

Airport Runway Reconstruction

An 11,000 ft primary runway rebuilt in night closures and short weekend windows, without delaying a morning departure.

Owner
Confidential
Region
U.S. Southeast
Market
Aviation
Capital value
$260M
Size
11,000 ft runway
Delivery
CM/GC
Duration
30 months
Completed
2025
The challenge

What was at stake.

The runway could close only at night and during a few longer weekend windows. Every closure had to end with a safe, inspected surface before the first flight. Paving production, lighting and navigation aid work had to fit inside those windows exactly.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Closure by closure

Each night closure was planned as its own schedule with production targets, inspection time and reopening checks.

02

Production tracking

Paving quantities were measured every night against the plan, so a short night was recovered in the next window.

03

Weather risk

Monte Carlo analysis on weather days showed the owner how many spare windows the program really needed.

04

Stakeholder look-ahead

Airlines and air traffic control received a two-week closure look-ahead drawn from the updated schedule.

Results

The result.

0Late runway reopenings
$260MCapital controlled
30Months of night closures
11,000 ftRunway rebuilt

Every night on a runway is a small project with a hard finish. We planned four hundred of them.

Lead scheduler, AdenTurton
Aviation