Washington, D.C. · Est. 2021 Project controls & construction IT CareersPartnersProgram RatesMedia512-908-5223Data date
Transportation · U.S. Midwest & Mountain

Bus Rapid Transit Corridor

A 14-mile bus rapid transit corridor with 22 stations, opened for revenue service on the date the city had announced.

Owner
Confidential
Region
U.S. Midwest & Mountain
Market
Transportation
Capital value
$330M
Size
14 miles · 22 stations
Delivery
CM/GC
Duration
32 months
Completed
2025
The challenge

What was at stake.

Federal grant milestones, private utility relocations and a public opening date all had to align. Utility owners worked on their own schedules and were often late. The agency needed to see early how utility delays would hit stations and the opening.

Schedule32 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
32 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Utility schedule

Every utility relocation was loaded into the CM/GC schedule with its own owner, logic and float to the station it blocked.

02

Grant milestones

Federal grant milestones were tracked as hard dates, with monthly reporting on float to each.

03

Station by station

Each station had its own readiness milestone, from platform to fare equipment to signal priority testing.

04

Delay records

Contemporaneous delay records and time impact analysis kept utility delay costs with the parties who caused them.

Results

The result.

On dateRevenue service started
$330MCapital controlled
32Months to opening
22Stations tracked

Utility delays always feel like nobody's fault. A time impact analysis makes them somebody's fact.

Claims analyst, AdenTurton
Transportation