Transportation · U.S. West

Light Rail Maintenance & Storage Facility

A light rail maintenance shop and storage yard, scheduled to receive the first new vehicle on the date it arrives.

Owner
Confidential
Region
U.S. West
Market
Transportation
Capital value
$280M
Size
28-acre yard · 60 vehicles
Delivery
CM at-risk
Duration
30 months
Status
In progress · 2026
The challenge

What is at stake.

New light rail vehicles are delivered on the manufacturer's schedule, and the agency has nowhere else to put them. Yard track, overhead power, the shop and its lifts must be ready, tested and certified first. Track, systems and building contractors all work in the same yard.

Schedule30 monthsIn progress · finish 2026
202420252026
Today
Start
2024
Planned finish
2026
Time elapsed
96%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Vehicle-first logic

The schedule is built backward from the first vehicle delivery through yard track, traction power and shop readiness.

02

Interfaces mapped

Every handoff between track, systems and building contractors is a named milestone with its own float.

03

Weekly coordination

A two-week look-ahead coordinates crews sharing yard access, drawn from the updated schedule.

04

Change control

Changes from the vehicle manufacturer are priced and their schedule effect shown before approval.

Results

Where it stands.

$280MCapital under control
30Months to first vehicle
28 acresYard in one schedule
60Vehicles to be housed

Vehicles show up whether the yard is ready or not. So the first vehicle is the first milestone we protect.

Senior scheduler, AdenTurton
Transportation