Data Center Campus Substation & Power Delivery

A 345 kV substation and medium-voltage distribution energized ahead of a campus's first data hall.

Owner
Confidential
Region
U.S. Texas
Market
Data Centers
Capital value
$420M
Size
345 kV · 300 MW
Delivery
EPC
Duration
24 months
Completed
2026
The challenge

What was at stake.

Utility interconnection, transformer delivery and outage windows on the transmission system were outside the owner's control, yet every data hall depended on them. Large power transformers had lead times longer than the building schedule. The owner needed to see the power path and its risk every month.

Schedule24 monthsCompleted 2026
202420252026
Start
2024
Finish
2026
Duration
24 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Power path schedule

Interconnection approvals, transformer manufacturing, outages and energization were scheduled as one chain tied to each data hall.

02

Vendor oversight

Transformer and breaker manufacturing progress was tracked monthly from the factory, with test dates in the schedule.

03

Outage planning

Transmission outage requests were lined up with construction readiness, so no window was wasted.

04

Risk analysis

Monte Carlo analysis on the energization date showed the owner exactly how much float the power path really had.

Results

The result.

AheadEnergized before the first hall
$420MCapital controlled
24Months to energization
300 MWPower delivered

The building can be perfect and still sit dark. Power is the first critical path on any data center campus.

Project controls manager, AdenTurton