Powered Shell to Colocation Data Center Conversion

A powered shell converted into two live colocation data halls, with the first tenant moving in on its lease date.

Owner
Confidential
Region
U.S. Southeast
Market
Data Centers
Capital value
$310M
Size
36 MW · 2 data halls
Delivery
Design-Build
Duration
18 months
Completed
2023
The challenge

What was at stake.

The tenant's lease had a fixed ready-for-service date and daily credits after it. The existing shell needed new structure for rooftop equipment, a new electrical yard and a full cooling plant. The first schedule we reviewed had commissioning compressed into two weeks.

Schedule18 monthsCompleted 2023
20222023
Start
2022
Finish
2023
Duration
18 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Honest review

Our schedule review showed commissioning needed nine weeks, not two, and that the finish date was already at risk.

02

Recovery sequence

We resequenced the electrical yard and cooling plant so L3 and L4 testing could start in the first hall while the second was still in build.

03

Commissioning tracked

Each system was tracked through L1 to L5, with open issues logged against the hall they blocked.

04

Weekly reporting

The owner and tenant received the same weekly report: date, float and the open commissioning issues.

Results

The result.

On dateFirst tenant ready for service
$310MCapital controlled
18Months, shell to live halls
36 MWIT capacity delivered

Two weeks of commissioning on a data hall is not a plan. It is a delay nobody has admitted yet.

Recovery lead, AdenTurton
Data Centers

Planning something like this?

Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.