Healthcare · U.S. Southeast

Hospital Central Utility Plant Replacement

A new central utility plant for a medical campus, cut over from the old plant without one unplanned loss of power, steam or chilled water.

Owner
Confidential
Region
U.S. Southeast
Market
Healthcare
Capital value
$120M
Size
18 MW · 6,000 tons cooling
Delivery
Design-Build
Duration
28 months
Completed
2025
The challenge

What was at stake.

Every building on the campus depended on the old plant, and it was failing. The new plant had to be built, commissioned and cut over one system at a time, with each outage approved by facilities and clinical leadership. The design-builder's schedule showed construction but not the outage sequence that decided the finish.

Schedule28 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
28 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Outages as activities

Each utility cutover was a named activity with its own prerequisites, approvals and backout plan, linked to the work it depended on.

02

Commissioning levels

Chillers, boilers, generators and switchgear were tracked through L1 to L5 commissioning, so readiness was measured, not assumed.

03

Weather windows

Chilled water cutovers were placed in cool months and steam cutovers in mild ones, with the schedule showing what a missed window would cost.

04

Change control

Every field change was priced and its schedule effect shown before approval, keeping the guaranteed price intact.

Results

The result.

0Unplanned utility outages
$120MCapital controlled
28Months to final cutover
L1 to L5Commissioning tracked

In a utility plant the outage plan is the schedule. Everything else is just getting ready for the outage.

Project controls manager, AdenTurton
Healthcare